Expansion of Hong Kong International Airport into a Three-Runway System Construction Phase Monthly EM&A Report No.11 (For November 2016) December 2016 Airport Authority Hong Kong 20/F AIA Kowloon Tower Landmark East 100 How Ming Street Kwun Tong Kowloon Hong Kong T +852 2828 5757 F +852 2827 1823 mottmac.hk Expansion of Hong Kong International Airport into a 355482 06/14/08 A Three-Runway System Mott MacDonald Construction Phase Monthly EM&A Report No.11 (For November 2016) December 2016 Airport Authority Hong Kong This Monthly EM&A Report No. 11 has been reviewed and certified by the Environmental Team Leader (ETL) in accordance with Condition 3.5 of Environmental Permit No. EP-489/2014. Certified by: Terence Kong Environmental Team Leader (ETL) Mott MacDonald Hong Kong Limited Date 5 January 2017 AECOM +852 3922 9000 tel 8/F, Grand Central Plaza, Tower 2, +852 2317 7609 fax 138 Shatin Rural Committee Road, Shatin, Hong Kong 香港新界沙田鄉事會路138號新城 市中央廣場第2座8樓 www.aecom.com Our Ref : 60440482/C/JCHL170105 By Email Airport Authority Hong Kong HKIA Tower, 1 Sky Plaza Road Hong Kong International Airport Lantau, Hong Kong Attn: Mr. Lawrence Tsui, Senior Manager 5 January 2017 Dear Sir, Contract No. 3102 3RS Independent Environmental Checker Consultancy Services Submission of Revised Monthly EM&A Report No.11 (November 2016) Reference is made to the Environmental Team’s submission of the revised Monthly EM&A Report No.11 under Condition 3.5 of the Environmental Permit No. EP-489/2014 certified by the ET Leader on 5 January 2017. We would like to inform you that we have no adverse comment on the captioned submission. Therefore we write to verify the captioned submission in accordance with the requirement stipulated in Condition 3.5 of EP-489/2014. Should you have any query, please feel free to contact our Roy Man at 3922 9365 or the undersigned at 3922 9376. Yours faithfully, AECOM Asia Co. Ltd. Jackel Law Independent Environmental Checker Mott MacDonald | Expansion of Hong Kong International Airport into a Three-Runway System Contents Executive Summary 1 1 Introduction 4 1.1 Background 4 1.2 Scope of this Report 4 1.3 Project Organisation 4 1.4 Summary of Construction Works 6 1.5 Summary of EM&A Programme Requirements 6 2 Air Quality Monitoring 8 2.1 Monitoring Stations 8 2.2 Monitoring Requirements and Schedule 8 2.3 Monitoring Equipment 8 2.4 Monitoring Methodology 8 2.4.1 Measuring Procedure 8 2.4.2 Maintenance and Calibration 9 2.5 Analysis and Interpretation of Monitoring Results 9 3 Noise Monitoring 10 3.1 Monitoring Stations 10 3.2 Monitoring Requirements and Schedule 10 3.3 Monitoring Equipment 10 3.4 Monitoring Methodology 11 3.4.1 Monitoring Procedure 11 3.4.2 Maintenance and Calibration 11 3.5 Analysis and Interpretation of Monitoring Results 11 4 Water Quality Monitoring 13 4.1 Monitoring Stations 13 4.2 Monitoring Requirements and Schedule 14 4.2.1 Action and Limit Levels for Water Quality Monitoring 14 4.3 Monitoring Equipment 15 4.4 Monitoring Methodology 15 4.4.1 Measuring Procedure 15 4.4.2 Maintenance and Calibration 16 4.4.3 Laboratory Measurement / Analysis 16 4.5 Analysis and Interpretation of Monitoring Results 16 Mott MacDonald | Expansion of Hong Kong International Airport into a Three-Runway System 4.5.1 Summary of Monitoring Results 16 4.5.2 Summary of Findings for Investigation of Exceedances 17 5 Waste Management 24 5.1 Monitoring Requirements 24 5.2 Waste Management Status 24 6 Chinese White Dolphin Monitoring 25 6.1 CWD Monitoring Requirements 25 6.2 CWD Monitoring Transects and Stations 25 6.2.1 Small Vessel Line-transect Survey 25 6.2.2 Land-based Theodolite Tracking 27 6.3 CWD Monitoring Methodology 27 6.3.1 Small Vessel Line-transect Survey 27 6.3.2 Photo Identification 28 6.3.3 Land-based Theodolite Tracking 28 6.4 Monitoring Results and Observations 29 6.4.1 Small Vessel Line-transect Survey 29 6.4.2 Photo Identification 32 6.4.3 Land-based Theodolite Tracking 32 6.5 Progress Update on Passive Acoustic Monitoring 33 6.6 Site Audit for CWD-related Mitigation Measures 33 6.7 Timing of Reporting CWD Monitoring Results 34 6.8 Summary of CWD Monitoring 34 7 Environmental Site Inspection and Audit 35 7.1 Environmental Site Inspection 35 7.2 Audit of Route Diversion and Speed Control of the SkyPier High Speed Ferries 35 7.3 Audit of Construction and Associated Vessels 37 7.4 Ecological Monitoring 37 7.5 Status of Submissions under Environmental Permits 37 7.6 Compliance with Other Statutory Environmental Requirements 38 7.7 Analysis and Interpretation of Complaints, Notification of Summons and Status of Prosecutions 38 7.7.1 Complaints 38 7.7.2 Notifications of Summons or Status of Prosecution 38 7.7.3 Cumulative Statistics 38 8 Future Key Issues and Other EIA & EM&A Issues 39 8.1 Construction Programme for the Coming Reporting Period 39 8.2 Key Environmental Issues for the Coming Reporting Period 39 8.3 Monitoring Schedule for the Coming Reporting Period 40 Mott MacDonald | Expansion of Hong Kong International Airport into a Three-Runway System 9 Conclusion and Recommendation 41 Tables Table 1.1: Contact Information of Key Personnel 4 Table 1.2: Summary of status for all environmental aspects under the Updated EM&A Manual 6 Table 2.1: Locations of Impact Air Quality Monitoring Stations 8 Table 2.2: Action and Limit Levels for 1-hour TSP 8 Table 2.3: Air Quality Monitoring Equipment 8 Table 2.4: Summary of 1-hour TSP Monitoring Results 9 Table 3.1: Locations of Impact Noise Monitoring Stations 10 Table 3.2: Action and Limit Levels for Construction Noise 10 Table 3.3: Noise Monitoring Equipment 11 Table 3.4: Summary of Construction Noise Monitoring Results 12 Table 4.1: Monitoring Locations and Parameters for Impact Water Quality Monitoring 13 Table 4.2: Action and Limit Levels for General Water Quality Monitoring and Regular DCM Monitoring 14 Table 4.3: The Control and Impact Stations during Flood Tide and Ebb Tide for General Water Quality Monitoring and Regular DCM Monitoring 15 Table 4.4: Water Quality Monitoring Equipment 15 Table 4.5: Laboratory Measurement/ Analysis of SS and Heavy Metals 16 Table 4.6: Summary of SS Compliance Status at IM Stations (Mid-Ebb Tide) 17 Table 4.7: Summary of Findings from Investigations of SS Exceedance during Mid-Ebb Tide 18 Table 4.8: Summary of SS Compliance Status at IM Stations (Mid-Flood Tide) 19 Table 4.9: Summary of Findings from Investigations of SS Exceedance during Mid-Flood Tide 19 Table 4.10: Summary of Turbidity Compliance Status at IM Stations (Mid-Ebb Tide) 20 Table 4.11: Summary of Turbidity Compliance Status at IM Stations (Mid-Flood Tide) 21 Table 4.12: Summary of Nickel Compliance Status at IM Stations (Mid-Flood Tide) 22 Table 5.1: Action and Limit Levels for Construction Waste 24 Table 6.1: Derived Values of Action Level (AL) and Limit Level (LL) for Chinese White Dolphin Monitoring 25 Table 6.2: Coordinates of Transect Lines in NEL, NWL, AW, WL and SWL Survey Areas 26 Table 6.3: Land-based Survey Station Details 27 Table 6.4: Comparison of CWD Encounter Rates of the Whole Survey Area with Action Levels 31 Table 6.5: Summary of Photo Identification 32 Table 6.6: Summary of Survey Effort and CWD Group of Land-based Theodolite Tracking 32 Table 7.1: Summary of Key Audit Findings against the SkyPier Plan 36 Table 7.2: Status of Submissions under Environmental Permit 38 Mott MacDonald | Expansion of Hong Kong International Airport into a Three-Runway System Figures Figure 1.1- 1.2 Key Construction Areas in this reporting period Figure 2.1 Locations of Air and Noise Monitoring Stations and Chek Lap Kok Wind Station Figure 3.1 Locations of Water Quality Monitoring Stations Figure 6.1 Vessel based Dolphin Monitoring Transects in Baseline Monitoring Figure 6.2 Land based Dolphin Monitoring in Baseline and Construction Phases Figure 6.3 Sightings Distribution of Chinese White Dolphins Figure 6.4 Plots of First Sightings of All CWD Groups obtained from Land-based Stations Figure 6.5 Location for Autonomous Passive Acoustic Monitoring in Baseline and Construction Phases Figure 7.1 Duration of the SkyPier HSFs travelled through the SCZ for 1 – 30 November 2016 Appendices Appendix A Environmental Mitigation Implementation Schedule (EMIS) for Construction Phase Appendix B Calibration Certificates Appendix C Monitoring Schedule Appendix D Monitoring Results Appendix E Status of Environmental Permits and Licences Appendix F Cumulative Statistics on Exceedances, Environmental Complaints, Notification of Summons and Status of Prosecutions Appendix G Data of SkyPier HSF Movements to/from Zhuhai and Macau (between 1 and 30 November 2016) Mott MacDonald | Expansion of Hong Kong International Airport into a Three-Runway System 1 Executive Summary The “Expansion of Hong Kong International Airport into a Three-Runway System” (the Project) serves to meet the future air traffic demands at Hong Kong International Airport (HKIA). On 7 November 2014, the Environmental Impact Assessment (EIA) Report (Register No.: AEIAR- 185/2014) for the Project was approved and an Environmental Permit (EP) (Permit No.: EP- 489/2014) was issued for the construction and operation of the Project. Airport Authority Hong Kong (AAHK) commissioned Mott MacDonald Hong Kong Limited (MMHK) to undertake the role of Environmental Team (ET) for carrying out the Environmental Monitoring & Audit (EM&A) works during the construction phase of the Project in accordance with the Updated EM&A Manual. This is the 11th Construction Phase Monthly EM&A Report for the Project which summarizes the monitoring results and audit findings of the EM&A programme during the reporting period from 1 November 2016 to 30 November 2016. Key Activities in the Reporting Period The key activities of the Project carried out in the reporting month were related to advanced works contract, which involved pilot hole drilling using Horizontal Directional Drilling (HDD) method at launching site, stockpiling of excavated materials from HDD operation at stockpiling area and casing installation on Sheung Sha Chau Island. CLP cable diversion enabling work contract was also carried out, which involved construction of drawpit, installation and backfilling for cable trough at the western part of the airport. The four in-progress deep cement mixing (DCM) contracts involved site investigation works, laying of geotextile and sand blanket. EM&A Activities Conducted in the Reporting Period The monthly EM&A programme was undertaken in accordance with the Updated EM&A Manual of the Project. During the reporting period, the ET conducted 33 sets of construction dust measurements, 21 sets of construction noise measurements, 13 events of water quality measurements, one round of terrestrial ecology monitoring on Sheung Sha Chau Island, two complete sets of small vessel line-transect surveys and five days of land-based theodolite tracking survey effort for Chinese White Dolphin (CWD) monitoring as well as landscape & visual and waste monitoring. Weekly site inspections of the construction works were carried out by the ET to audit the implementation of proper environmental pollution control and mitigation measures for the Project. Bi-weekly site inspections were also conducted by the Independent Environmental Checker (IEC). Observations have been recorded in the site inspection checklists and provided to the contractors together with the appropriate follow-up actions where necessary. On the implementation of Marine Mammal Watching Plan, trainings for the dolphin observers were provided by the ET prior to the deployment of silt curtain, with the training records kept by the ET. Visual inspection and integrity check for silt curtain were carried out by the contractor and their daily records were audited by ET and IEC during site inspection. Audits of acoustic decoupling for construction vessels and Skypier High Speed Ferries route diversion and speed control and construction vessel management were carried out by the ET. Mott MacDonald | Expansion of Hong Kong International Airport into a Three-Runway System 2 On the implementation of the Marine Travel Routes and Management Plan for High Speed Ferries of SkyPier (the SkyPier Plan), the daily movements of all SkyPier High Speed Ferries (HSFs) in November 2016 were in the range of 88 to 93 daily movements, which are within the maximum daily cap of 125 daily movements. A total of 837 HSF movements under the SkyPier Plan were recorded in the reporting period. All HSFs had travelled through the SCZ with average speeds under 15 knots (8.5 to 14.2 knots), which were in compliance with the SkyPier Plan, except that one HSF travelled with an average speed of 16.4 knots. Notice regarding the exceedance of average speed within SCZ was sent to the ferry operator and the case is under investigation by ET. One ferry movement not following the diverted route and four ferry movements with minor deviation from the diverted route are under investigation by ET. The investigation result will be presented in the next monthly EM&A report. In summary, the ET and IEC have audited the HSF movements against the SkyPier Plan and conducted follow up investigation or actions accordingly. On the implementation of the Marine Travel Routes and Management Plan for Construction and Associated Vessel (MTRMP-CAV), ET had conducted weekly audit of relevant information, including AIS data, vessel tracks and other relevant records to ensure the contractors complied with the requirements of the MTRMP-CAV. Training has been provided for the concerned skippers to facilitate them in familiarising with the requirements of the MTRMP-CAV. 3-month rolling programmes for construction vessel activities were also received from contractors. Results of Impact Monitoring All the monitoring works for construction dust, construction noise, water quality, construction waste, terrestrial ecology and CWD were conducted during the reporting period in accordance with the Updated EM&A Manual. No exceedance of the Action or Limit Levels in relation to the construction dust, construction noise, construction waste and CWD monitoring was recorded in the reporting month. The water quality monitoring results for dissolved oxygen (DO), total alkalinity and chromium obtained during the reporting period were in compliance with their corresponding Action and Limit Levels. For turbidity, suspended solids (SS) and nickel, some of the testing results had exceeded the relevant Action or Limit Levels during the reporting period. The summary of exceedances are presented in Section 4.5.2. Investigations were carried out immediately for each of the exceedance cases, and the investigation findings concluded that all the exceedances were not due to the Project. The monthly terrestrial ecology monitoring on Sheung Sha Chau Island observed that installation of casing was conducted on the Island and there was no encroachment upon the egretry area nor any significant disturbance to the egrets at Sheung Sha Chau by the works. Summary of Upcoming Key Issues Key activities anticipated in the next reporting period for the Project will include the following contract works: Advanced Works Contract: Contract P560 (R) Aviation Fuel Pipeline Diversion Works ● HDD pilot hole drilling; ● Stockpiling of excavated materials from HDD operation; ● Casing installation. Reclamation Contracts:
Description: